A performance guarantee test in an electronic systems contract is conducted to:
- Verify that the installed system meets the specified performance requirements before acceptance
- Select the winning bidder
- Train the owner's staff only
- Determine the contractor's profit
Answer
A. Verify that the installed system meets the specified performance requirements before acceptance
Solution
Also called acceptance testing or commissioning.
More ECE questions
- An extension of contract time is usually justified when delay is caused by:
- 'Time is of the essence' in a contract means that:
- A subcontractor is a party who:
- Substantial completion of a project means that:
- A 'punch list' prepared near the end of a project contains:
- A 'Request for Information' (RFI) in a project is used by the contractor to:
- When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
- In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
- In which type of contract does the OWNER bear the greatest risk of cost overruns?
- The period after completion during which the contractor must repair defects at its own cost is the: