In which type of contract does the OWNER bear the greatest risk of cost overruns?

  1. Lump-sum
  2. Firm fixed-price
  3. Unit-price with fixed quantities
  4. Cost-plus-percentage-of-cost

Answer

D. Cost-plus-percentage-of-cost

Solution

The contractor's fee rises with cost, giving little incentive to control costs.

More ECE questions

  1. The period after completion during which the contractor must repair defects at its own cost is the:
  2. A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
  3. The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…
  4. A contract clause that allows the price to be adjusted when material or labor costs change significantly is called an:
  5. A clause excusing performance when events beyond the parties' control (e.g., war, natural disasters) prevent it is called a:
  6. A document listing the items of work with their quantities, used for pricing bids, is the:
  7. Detailed drawings prepared by the contractor or supplier showing how equipment will be fabricated or installed are called:
  8. Drawings that show the final installed configuration of a system, including field changes, are called:
  9. A security submitted with a bid to guarantee that the bidder will enter into the contract if awarded is called a:
  10. A portion of each progress payment withheld by the owner to ensure proper completion of the work is called:

All ECE questions