Engineering Board Exam Reviewer · ECE · easy
A clause excusing performance when events beyond the parties' control (e.g., war, natural disasters) prevent it is called a:
- Liquidated damages clause
- Escalation clause
- Force majeure clause
- Retention clause
Answer
C. Force majeure clause
Solution
It reflects the principle of fortuitous events.
More ECE questions
- A document listing the items of work with their quantities, used for pricing bids, is the:
- Detailed drawings prepared by the contractor or supplier showing how equipment will be fabricated or installed are called:
- Drawings that show the final installed configuration of a system, including field changes, are called:
- A security submitted with a bid to guarantee that the bidder will enter into the contract if awarded is called a:
- A portion of each progress payment withheld by the owner to ensure proper completion of the work is called:
- A formal written order issued after contract award that modifies the scope, price or time of the contract is called a:
- A 'turnkey' contract means the contractor delivers:
- A contract in which the owner pays the contractor's actual costs plus an agreed fee or percentage is called a:
- A contract in which payment is based on measured quantities of work multiplied by agreed rates is called a:
- A construction contract in which the contractor agrees to complete the entire work for a fixed total price is called a: