Engineering Board Exam Reviewer · ECE · easy
Drawings that show the final installed configuration of a system, including field changes, are called:
- Shop drawings
- As-built drawings
- Schematic diagrams
- Bid drawings
Answer
B. As-built drawings
Solution
They are submitted at project completion.
More ECE questions
- A security submitted with a bid to guarantee that the bidder will enter into the contract if awarded is called a:
- A portion of each progress payment withheld by the owner to ensure proper completion of the work is called:
- A formal written order issued after contract award that modifies the scope, price or time of the contract is called a:
- A 'turnkey' contract means the contractor delivers:
- A contract in which the owner pays the contractor's actual costs plus an agreed fee or percentage is called a:
- A contract in which payment is based on measured quantities of work multiplied by agreed rates is called a:
- A construction contract in which the contractor agrees to complete the entire work for a fixed total price is called a:
- A building completed in 2010 collapsed in 2022 because of a defect in the structural plans. Within what period must the owner file the…
- A contract to supply surveillance equipment for an illegal gambling operation is:
- A verbal agreement was made on January 2, 2024 to maintain a company's PABX system for two years, starting the following month. The…