A building completed in 2010 collapsed in 2022 because of a defect in the structural plans. Within what period must the owner file the action against the designer under Article 1723?

  1. Within 4 years from completion in 2010
  2. Within 15 years from completion only
  3. No action is possible because 12 years have passed
  4. Within 10 years from the collapse in 2022

Answer

D. Within 10 years from the collapse in 2022

Solution

The designer is liable if the collapse occurs within 15 years from completion; the action must be brought within 10 years after the collapse.

More ECE questions

  1. A contract to supply surveillance equipment for an illegal gambling operation is:
  2. A verbal agreement was made on January 2, 2024 to maintain a company's PABX system for two years, starting the following month. The…
  3. A 17-year-old student signs a contract with a computer shop to buy a laptop on installment without parental consent. When the student…
  4. An ECE contractor agreed in writing to install a fiber network for a subdivision. Before work began, the developer discovered that the…
  5. Damages awarded to vindicate a right that has been violated even if no actual loss is proven are:
  6. Damages imposed by way of example or correction for the public good, in addition to other damages, are:
  7. Damages awarded to compensate for actual pecuniary loss that has been duly proven are called:
  8. Liquidated damages in a contract are:
  9. Simulation of contract where the parties do not intend to be bound at all is called:
  10. A contract that is entered into by both parties who are incapable of giving consent (e.g., both are minors) is:

All ECE questions