A portion of each progress payment withheld by the owner to ensure proper completion of the work is called:
- Advance payment
- Bid security
- Retention money
- Liquidated damages
Answer
C. Retention money
Solution
It is released after completion and acceptance, often against a warranty guarantee.
More ECE questions
- A formal written order issued after contract award that modifies the scope, price or time of the contract is called a:
- A 'turnkey' contract means the contractor delivers:
- A contract in which the owner pays the contractor's actual costs plus an agreed fee or percentage is called a:
- A contract in which payment is based on measured quantities of work multiplied by agreed rates is called a:
- A construction contract in which the contractor agrees to complete the entire work for a fixed total price is called a:
- A building completed in 2010 collapsed in 2022 because of a defect in the structural plans. Within what period must the owner file the…
- A contract to supply surveillance equipment for an illegal gambling operation is:
- A verbal agreement was made on January 2, 2024 to maintain a company's PABX system for two years, starting the following month. The…
- A 17-year-old student signs a contract with a computer shop to buy a laptop on installment without parental consent. When the student…
- An ECE contractor agreed in writing to install a fiber network for a subdivision. Before work began, the developer discovered that the…