Engineering Board Exam Reviewer · ECE · easy

A construction contract in which the contractor agrees to complete the entire work for a fixed total price is called a:

  1. Unit-price contract
  2. Cost-plus contract
  3. Lump-sum (fixed-price) contract
  4. Time-and-materials contract

Answer

C. Lump-sum (fixed-price) contract

Solution

The contractor bears most of the cost risk.

More ECE questions

  1. A building completed in 2010 collapsed in 2022 because of a defect in the structural plans. Within what period must the owner file the…
  2. A contract to supply surveillance equipment for an illegal gambling operation is:
  3. A verbal agreement was made on January 2, 2024 to maintain a company's PABX system for two years, starting the following month. The…
  4. A 17-year-old student signs a contract with a computer shop to buy a laptop on installment without parental consent. When the student…
  5. An ECE contractor agreed in writing to install a fiber network for a subdivision. Before work began, the developer discovered that the…
  6. Damages awarded to vindicate a right that has been violated even if no actual loss is proven are:
  7. Damages imposed by way of example or correction for the public good, in addition to other damages, are:
  8. Damages awarded to compensate for actual pecuniary loss that has been duly proven are called:
  9. Liquidated damages in a contract are:
  10. Simulation of contract where the parties do not intend to be bound at all is called: