Engineering Board Exam Reviewer · ECE · easy

The period after completion during which the contractor must repair defects at its own cost is the:

  1. Mobilization period
  2. Bidding period
  3. Construction period
  4. Defects liability (warranty) period

Answer

D. Defects liability (warranty) period

Solution

Retention or a warranty security usually covers this obligation.

More ECE questions

  1. A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
  2. The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…
  3. A contract clause that allows the price to be adjusted when material or labor costs change significantly is called an:
  4. A clause excusing performance when events beyond the parties' control (e.g., war, natural disasters) prevent it is called a:
  5. A document listing the items of work with their quantities, used for pricing bids, is the:
  6. Detailed drawings prepared by the contractor or supplier showing how equipment will be fabricated or installed are called:
  7. Drawings that show the final installed configuration of a system, including field changes, are called:
  8. A security submitted with a bid to guarantee that the bidder will enter into the contract if awarded is called a:
  9. A portion of each progress payment withheld by the owner to ensure proper completion of the work is called:
  10. A formal written order issued after contract award that modifies the scope, price or time of the contract is called a:

All ECE questions