Engineering Board Exam Reviewer · ECE · medium
An extension of contract time is usually justified when delay is caused by:
- The contractor's poor planning
- Events beyond the contractor's control, such as owner-caused delays or force majeure
- The contractor's lack of manpower
- The contractor's financial problems
Answer
B. Events beyond the contractor's control, such as owner-caused delays or force majeure
Solution
Excusable delays entitle the contractor to more time; inexcusable delays may trigger liquidated damages.
More ECE questions
- 'Time is of the essence' in a contract means that:
- A subcontractor is a party who:
- Substantial completion of a project means that:
- A 'punch list' prepared near the end of a project contains:
- A 'Request for Information' (RFI) in a project is used by the contractor to:
- When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
- In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
- In which type of contract does the OWNER bear the greatest risk of cost overruns?
- The period after completion during which the contractor must repair defects at its own cost is the:
- A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the: