Engineering Board Exam Reviewer · ECE · medium

An extension of contract time is usually justified when delay is caused by:

  1. The contractor's poor planning
  2. Events beyond the contractor's control, such as owner-caused delays or force majeure
  3. The contractor's lack of manpower
  4. The contractor's financial problems

Answer

B. Events beyond the contractor's control, such as owner-caused delays or force majeure

Solution

Excusable delays entitle the contractor to more time; inexcusable delays may trigger liquidated damages.

More ECE questions

  1. 'Time is of the essence' in a contract means that:
  2. A subcontractor is a party who:
  3. Substantial completion of a project means that:
  4. A 'punch list' prepared near the end of a project contains:
  5. A 'Request for Information' (RFI) in a project is used by the contractor to:
  6. When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
  7. In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
  8. In which type of contract does the OWNER bear the greatest risk of cost overruns?
  9. The period after completion during which the contractor must repair defects at its own cost is the:
  10. A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:

All ECE questions