Engineering Board Exam Reviewer · ECE · medium
A 'punch list' prepared near the end of a project contains:
- Minor items of work that remain to be completed or corrected before final acceptance
- The list of bidders
- The contractor's payroll
- The project budget
Answer
A. Minor items of work that remain to be completed or corrected before final acceptance
Solution
Final payment is usually released after punch-list items are completed.
More ECE questions
- A 'Request for Information' (RFI) in a project is used by the contractor to:
- When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
- In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
- In which type of contract does the OWNER bear the greatest risk of cost overruns?
- The period after completion during which the contractor must repair defects at its own cost is the:
- A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
- The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…
- A contract clause that allows the price to be adjusted when material or labor costs change significantly is called an:
- A clause excusing performance when events beyond the parties' control (e.g., war, natural disasters) prevent it is called a:
- A document listing the items of work with their quantities, used for pricing bids, is the: