Engineering Board Exam Reviewer · ECE · medium

A 'punch list' prepared near the end of a project contains:

  1. Minor items of work that remain to be completed or corrected before final acceptance
  2. The list of bidders
  3. The contractor's payroll
  4. The project budget

Answer

A. Minor items of work that remain to be completed or corrected before final acceptance

Solution

Final payment is usually released after punch-list items are completed.

More ECE questions

  1. A 'Request for Information' (RFI) in a project is used by the contractor to:
  2. When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
  3. In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
  4. In which type of contract does the OWNER bear the greatest risk of cost overruns?
  5. The period after completion during which the contractor must repair defects at its own cost is the:
  6. A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
  7. The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…
  8. A contract clause that allows the price to be adjusted when material or labor costs change significantly is called an:
  9. A clause excusing performance when events beyond the parties' control (e.g., war, natural disasters) prevent it is called a:
  10. A document listing the items of work with their quantities, used for pricing bids, is the:

All ECE questions