When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule is that:

  1. Drawings always govern over specifications
  2. Specifications usually govern over drawings, and figured dimensions over scaled dimensions
  3. The contractor chooses the cheaper option
  4. The work stops permanently

Answer

B. Specifications usually govern over drawings, and figured dimensions over scaled dimensions

Solution

Most contracts include an order-of-precedence clause; ambiguities should be clarified with the engineer.

More ECE questions

  1. In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
  2. In which type of contract does the OWNER bear the greatest risk of cost overruns?
  3. The period after completion during which the contractor must repair defects at its own cost is the:
  4. A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
  5. The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…
  6. A contract clause that allows the price to be adjusted when material or labor costs change significantly is called an:
  7. A clause excusing performance when events beyond the parties' control (e.g., war, natural disasters) prevent it is called a:
  8. A document listing the items of work with their quantities, used for pricing bids, is the:
  9. Detailed drawings prepared by the contractor or supplier showing how equipment will be fabricated or installed are called:
  10. Drawings that show the final installed configuration of a system, including field changes, are called:

All ECE questions