When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule is that:
- Drawings always govern over specifications
- Specifications usually govern over drawings, and figured dimensions over scaled dimensions
- The contractor chooses the cheaper option
- The work stops permanently
Answer
B. Specifications usually govern over drawings, and figured dimensions over scaled dimensions
Solution
Most contracts include an order-of-precedence clause; ambiguities should be clarified with the engineer.
More ECE questions
- In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
- In which type of contract does the OWNER bear the greatest risk of cost overruns?
- The period after completion during which the contractor must repair defects at its own cost is the:
- A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
- The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…
- A contract clause that allows the price to be adjusted when material or labor costs change significantly is called an:
- A clause excusing performance when events beyond the parties' control (e.g., war, natural disasters) prevent it is called a:
- A document listing the items of work with their quantities, used for pricing bids, is the:
- Detailed drawings prepared by the contractor or supplier showing how equipment will be fabricated or installed are called:
- Drawings that show the final installed configuration of a system, including field changes, are called: