Engineering Board Exam Reviewer · ECE · medium

'Time is of the essence' in a contract means that:

  1. The contract has no deadline
  2. Completion on or before the deadline is a material requirement, and delay is a substantial breach
  3. Payment must be made immediately
  4. Work can be performed only at night

Answer

B. Completion on or before the deadline is a material requirement, and delay is a substantial breach

Solution

Delay may justify termination and damages.

More ECE questions

  1. A subcontractor is a party who:
  2. Substantial completion of a project means that:
  3. A 'punch list' prepared near the end of a project contains:
  4. A 'Request for Information' (RFI) in a project is used by the contractor to:
  5. When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
  6. In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
  7. In which type of contract does the OWNER bear the greatest risk of cost overruns?
  8. The period after completion during which the contractor must repair defects at its own cost is the:
  9. A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
  10. The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…

All ECE questions