Engineering Board Exam Reviewer · ECE · medium

A subcontractor is a party who:

  1. Has a direct contract with the owner as the main contractor
  2. Supervises the main contractor for the owner
  3. Has a contract with the main contractor to perform part of the work
  4. Designs the project for the owner

Answer

C. Has a contract with the main contractor to perform part of the work

Solution

The main contractor remains responsible to the owner for subcontracted work.

More ECE questions

  1. Substantial completion of a project means that:
  2. A 'punch list' prepared near the end of a project contains:
  3. A 'Request for Information' (RFI) in a project is used by the contractor to:
  4. When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
  5. In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
  6. In which type of contract does the OWNER bear the greatest risk of cost overruns?
  7. The period after completion during which the contractor must repair defects at its own cost is the:
  8. A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
  9. The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…
  10. A contract clause that allows the price to be adjusted when material or labor costs change significantly is called an:

All ECE questions