Engineering Board Exam Reviewer · ECE · medium
A subcontractor is a party who:
- Has a direct contract with the owner as the main contractor
- Supervises the main contractor for the owner
- Has a contract with the main contractor to perform part of the work
- Designs the project for the owner
Answer
C. Has a contract with the main contractor to perform part of the work
Solution
The main contractor remains responsible to the owner for subcontracted work.
More ECE questions
- Substantial completion of a project means that:
- A 'punch list' prepared near the end of a project contains:
- A 'Request for Information' (RFI) in a project is used by the contractor to:
- When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
- In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
- In which type of contract does the OWNER bear the greatest risk of cost overruns?
- The period after completion during which the contractor must repair defects at its own cost is the:
- A clause stating that if one provision of the contract is held invalid, the rest remain in effect, is the:
- The government body in the Philippines with original and exclusive jurisdiction over construction disputes when parties agree to…
- A contract clause that allows the price to be adjusted when material or labor costs change significantly is called an: