Engineering Board Exam Reviewer · ECE · medium

Testing and commissioning of an installed system is generally done:

  1. Before the bidding process
  2. During the design stage only
  3. After the warranty expires
  4. After installation and before final acceptance by the owner

Answer

D. After installation and before final acceptance by the owner

Solution

It confirms that the system works as specified.

More ECE questions

  1. A performance guarantee test in an electronic systems contract is conducted to:
  2. An extension of contract time is usually justified when delay is caused by:
  3. 'Time is of the essence' in a contract means that:
  4. A subcontractor is a party who:
  5. Substantial completion of a project means that:
  6. A 'punch list' prepared near the end of a project contains:
  7. A 'Request for Information' (RFI) in a project is used by the contractor to:
  8. When there is a conflict between the drawings and the specifications and the contract is silent on precedence, the generally accepted rule…
  9. In which type of contract does the CONTRACTOR bear the greatest risk of cost overruns?
  10. In which type of contract does the OWNER bear the greatest risk of cost overruns?

All ECE questions