Engineering Board Exam Reviewer · ECE · hard
A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor finishes 25 days late with no valid excuse. How much are the liquidated damages?
- ₱1,250,000.00
- ₱5,000.00
- ₱12,500.00
- ₱125,000.00
Answer
D. ₱125,000.00
Solution
LD = 0.001 × ₱5,000,000 × 25 days = ₱125,000.00.