Engineering Board Exam Reviewer · ECE · hard

A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor finishes 25 days late with no valid excuse. How much are the liquidated damages?

  1. ₱1,250,000.00
  2. ₱5,000.00
  3. ₱12,500.00
  4. ₱125,000.00

Answer

D. ₱125,000.00

Solution

LD = 0.001 × ₱5,000,000 × 25 days = ₱125,000.00.

More ECE questions

  1. In a contract, a 'warranty' generally refers to:
  2. A Memorandum of Agreement (MOA) is generally:
  3. A non-disclosure agreement (NDA) is used to:
  4. A Service Level Agreement (SLA) in an ICT maintenance contract typically specifies:
  5. A 'scope of work' (SOW) document defines:
  6. Testing and commissioning of an installed system is generally done:
  7. A performance guarantee test in an electronic systems contract is conducted to:
  8. An extension of contract time is usually justified when delay is caused by:
  9. 'Time is of the essence' in a contract means that:
  10. A subcontractor is a party who:

All ECE questions