Engineering Board Exam Reviewer · ECE · hard
A ₱2,000,000 contract allows 10% retention on each progress billing. The first billing is for 30% of the work. Ignoring advance payment and taxes, how much will the contractor receive for this billing?
- ₱600,000.00
- ₱60,000.00
- ₱540,000.00
- ₱1,800,000.00
Answer
C. ₱540,000.00
Solution
Billing = 30% × 2,000,000 = ₱600,000. Retention = 10% × 600,000 = ₱60,000. Net = ₱540,000.00.
More ECE questions
- A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor…
- In a contract, a 'warranty' generally refers to:
- A Memorandum of Agreement (MOA) is generally:
- A non-disclosure agreement (NDA) is used to:
- A Service Level Agreement (SLA) in an ICT maintenance contract typically specifies:
- A 'scope of work' (SOW) document defines:
- Testing and commissioning of an installed system is generally done:
- A performance guarantee test in an electronic systems contract is conducted to:
- An extension of contract time is usually justified when delay is caused by:
- 'Time is of the essence' in a contract means that: