Engineering Board Exam Reviewer · ECE · hard
Under the RA 9184 IRR for infrastructure, liquidated damages equal one-tenth of one percent (0.1%) of the cost of the unperformed portion for every day of delay. A ₱10,000,000 project is 80% complete when the deadline passes and is finished 20 days late (assume the unperformed portion stays at 20% for simplicity). What are the liquidated damages?
- ₱200,000.00
- ₱40,000.00
- ₱160,000.00
- ₱400,000.00
Answer
B. ₱40,000.00
Solution
Unperformed portion = 20% × 10,000,000 = ₱2,000,000. LD = 0.001 × 2,000,000 × 20 = ₱40,000.00.
More ECE questions
- A ₱2,000,000 contract allows 10% retention on each progress billing. The first billing is for 30% of the work. Ignoring advance payment…
- A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor…
- In a contract, a 'warranty' generally refers to:
- A Memorandum of Agreement (MOA) is generally:
- A non-disclosure agreement (NDA) is used to:
- A Service Level Agreement (SLA) in an ICT maintenance contract typically specifies:
- A 'scope of work' (SOW) document defines:
- Testing and commissioning of an installed system is generally done:
- A performance guarantee test in an electronic systems contract is conducted to:
- An extension of contract time is usually justified when delay is caused by: