Engineering Board Exam Reviewer · ECE · hard
A contractor received a 15% advance payment on a ₱4,000,000 contract, to be recouped proportionally from progress billings. A billing for 25% of the work is submitted, with 10% retention. What net amount is paid for this billing?
- ₱750,000.00
- ₱900,000.00
- ₱850,000.00
- ₱1,000,000.00
Answer
A. ₱750,000.00
Solution
Gross = 25% × 4,000,000 = ₱1,000,000. Recoupment = 15% × 1,000,000 = ₱150,000. Retention = 10% × 1,000,000 = ₱100,000. Net = ₱750,000.
More ECE questions
- Under the RA 9184 IRR for infrastructure, liquidated damages equal one-tenth of one percent (0.1%) of the cost of the unperformed portion…
- A ₱2,000,000 contract allows 10% retention on each progress billing. The first billing is for 30% of the work. Ignoring advance payment…
- A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor…
- In a contract, a 'warranty' generally refers to:
- A Memorandum of Agreement (MOA) is generally:
- A non-disclosure agreement (NDA) is used to:
- A Service Level Agreement (SLA) in an ICT maintenance contract typically specifies:
- A 'scope of work' (SOW) document defines:
- Testing and commissioning of an installed system is generally done:
- A performance guarantee test in an electronic systems contract is conducted to: