Engineering Board Exam Reviewer · ECE · hard

Under a cost-plus-fixed-fee contract with a fixed fee of ₱150,000, the estimated cost was ₱1,500,000 but the actual cost was ₱1,800,000. What does the owner pay?

  1. ₱1,650,000.00
  2. ₱1,980,000.00
  3. ₱1,950,000.00
  4. ₱1,800,000.00

Answer

C. ₱1,950,000.00

Solution

Owner pays actual cost plus the fixed fee: ₱1,800,000 + ₱150,000 = ₱1,950,000. The fee does not increase with cost.

More ECE questions

  1. Under a cost-plus-10%-fee contract, the actual cost of a telecom shelter installation is ₱1,800,000. What does the owner pay in total?
  2. A unit-price contract specifies ₱850 per meter of installed cable. The estimate was 2,000 m, but the measured installed length is 2,350 m…
  3. A contractor received a 15% advance payment on a ₱4,000,000 contract, to be recouped proportionally from progress billings. A billing for…
  4. Under the RA 9184 IRR for infrastructure, liquidated damages equal one-tenth of one percent (0.1%) of the cost of the unperformed portion…
  5. A ₱2,000,000 contract allows 10% retention on each progress billing. The first billing is for 30% of the work. Ignoring advance payment…
  6. A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor…
  7. In a contract, a 'warranty' generally refers to:
  8. A Memorandum of Agreement (MOA) is generally:
  9. A non-disclosure agreement (NDA) is used to:
  10. A Service Level Agreement (SLA) in an ICT maintenance contract typically specifies:

All ECE questions