Under a cost-plus-10%-fee contract, the actual cost of a telecom shelter installation is ₱1,800,000. What does the owner pay in total?

  1. ₱1,800,000.00
  2. ₱180,000.00
  3. ₱2,000,000.00
  4. ₱1,980,000.00

Answer

D. ₱1,980,000.00

Solution

Total = cost + 10% fee = 1,800,000 × 1.10 = ₱1,980,000.00.

More ECE questions

  1. A unit-price contract specifies ₱850 per meter of installed cable. The estimate was 2,000 m, but the measured installed length is 2,350 m…
  2. A contractor received a 15% advance payment on a ₱4,000,000 contract, to be recouped proportionally from progress billings. A billing for…
  3. Under the RA 9184 IRR for infrastructure, liquidated damages equal one-tenth of one percent (0.1%) of the cost of the unperformed portion…
  4. A ₱2,000,000 contract allows 10% retention on each progress billing. The first billing is for 30% of the work. Ignoring advance payment…
  5. A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor…
  6. In a contract, a 'warranty' generally refers to:
  7. A Memorandum of Agreement (MOA) is generally:
  8. A non-disclosure agreement (NDA) is used to:
  9. A Service Level Agreement (SLA) in an ICT maintenance contract typically specifies:
  10. A 'scope of work' (SOW) document defines:

All ECE questions