Under Philippine procurement law, the default method of procurement is:
- Direct contracting
- Competitive (public) bidding
- Shopping
- Negotiated procurement
Answer
B. Competitive (public) bidding
Solution
Alternative methods are allowed only under specific conditions.
More ECE questions
- The Government Procurement Reform Act enacted in 2003 is:
- Under a cost-plus-fixed-fee contract with a fixed fee of ₱150,000, the estimated cost was ₱1,500,000 but the actual cost was ₱1,800,000…
- Under a cost-plus-10%-fee contract, the actual cost of a telecom shelter installation is ₱1,800,000. What does the owner pay in total?
- A unit-price contract specifies ₱850 per meter of installed cable. The estimate was 2,000 m, but the measured installed length is 2,350 m…
- A contractor received a 15% advance payment on a ₱4,000,000 contract, to be recouped proportionally from progress billings. A billing for…
- Under the RA 9184 IRR for infrastructure, liquidated damages equal one-tenth of one percent (0.1%) of the cost of the unperformed portion…
- A ₱2,000,000 contract allows 10% retention on each progress billing. The first billing is for 30% of the work. Ignoring advance payment…
- A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor…
- In a contract, a 'warranty' generally refers to:
- A Memorandum of Agreement (MOA) is generally: