Engineering Board Exam Reviewer · ECE · easy

Under Philippine procurement law, the default method of procurement is:

  1. Direct contracting
  2. Competitive (public) bidding
  3. Shopping
  4. Negotiated procurement

Answer

B. Competitive (public) bidding

Solution

Alternative methods are allowed only under specific conditions.

More ECE questions

  1. The Government Procurement Reform Act enacted in 2003 is:
  2. Under a cost-plus-fixed-fee contract with a fixed fee of ₱150,000, the estimated cost was ₱1,500,000 but the actual cost was ₱1,800,000…
  3. Under a cost-plus-10%-fee contract, the actual cost of a telecom shelter installation is ₱1,800,000. What does the owner pay in total?
  4. A unit-price contract specifies ₱850 per meter of installed cable. The estimate was 2,000 m, but the measured installed length is 2,350 m…
  5. A contractor received a 15% advance payment on a ₱4,000,000 contract, to be recouped proportionally from progress billings. A billing for…
  6. Under the RA 9184 IRR for infrastructure, liquidated damages equal one-tenth of one percent (0.1%) of the cost of the unperformed portion…
  7. A ₱2,000,000 contract allows 10% retention on each progress billing. The first billing is for 30% of the work. Ignoring advance payment…
  8. A contract for a ₱5,000,000 CCTV project provides liquidated damages of 0.1% of the contract price per day of delay. The contractor…
  9. In a contract, a 'warranty' generally refers to:
  10. A Memorandum of Agreement (MOA) is generally:

All ECE questions