Engineering Board Exam Reviewer · ECE · easy

Under RA 9184, consulting services are generally awarded to the bidder with the:

  1. Lowest Calculated Bid
  2. Lowest number of employees
  3. Highest Rated Responsive Bid
  4. Largest capital

Answer

C. Highest Rated Responsive Bid

Solution

Evaluation emphasizes technical quality.

More ECE questions

  1. Under RA 9184, contracts for goods and infrastructure are generally awarded to the bidder with the:
  2. The committee in a government agency responsible for conducting the procurement process is the:
  3. Under Philippine procurement law, the default method of procurement is:
  4. The Government Procurement Reform Act enacted in 2003 is:
  5. Under a cost-plus-fixed-fee contract with a fixed fee of ₱150,000, the estimated cost was ₱1,500,000 but the actual cost was ₱1,800,000…
  6. Under a cost-plus-10%-fee contract, the actual cost of a telecom shelter installation is ₱1,800,000. What does the owner pay in total?
  7. A unit-price contract specifies ₱850 per meter of installed cable. The estimate was 2,000 m, but the measured installed length is 2,350 m…
  8. A contractor received a 15% advance payment on a ₱4,000,000 contract, to be recouped proportionally from progress billings. A billing for…
  9. Under the RA 9184 IRR for infrastructure, liquidated damages equal one-tenth of one percent (0.1%) of the cost of the unperformed portion…
  10. A ₱2,000,000 contract allows 10% retention on each progress billing. The first billing is for 30% of the work. Ignoring advance payment…

All ECE questions