Engineering Board Exam Reviewer · Engineering Management · easy
The quality expert known for the 14 points for management and the PDCA cycle is:
- Joseph Juran
- Philip Crosby
- W. Edwards Deming
- Kaoru Ishikawa
Answer
C. W. Edwards Deming
Solution
PDCA = Plan, Do, Check (Study), Act — also called the Deming or Shewhart cycle.
More Engineering Management questions
- Shortening an activity's duration by adding resources at extra cost is called:
- The hierarchical decomposition of a project into smaller, manageable deliverables is called the:
- A dummy activity in an activity-on-arrow network:
- In PERT, the three time estimates for an activity are:
- The critical path in a project network is the:
- PERT stands for:
- The study that determines whether a proposed project is technically, economically and financially viable is called a:
- Porter's Five Forces model is used to analyze:
- In the BCG matrix, a business with high market share in a low-growth market is called a:
- A group creativity technique in which ideas are generated freely without criticism is called: