Engineering Board Exam Reviewer · Engineering Management · easy

The quality expert known for the 14 points for management and the PDCA cycle is:

  1. Joseph Juran
  2. Philip Crosby
  3. W. Edwards Deming
  4. Kaoru Ishikawa

Answer

C. W. Edwards Deming

Solution

PDCA = Plan, Do, Check (Study), Act — also called the Deming or Shewhart cycle.

More Engineering Management questions

  1. Shortening an activity's duration by adding resources at extra cost is called:
  2. The hierarchical decomposition of a project into smaller, manageable deliverables is called the:
  3. A dummy activity in an activity-on-arrow network:
  4. In PERT, the three time estimates for an activity are:
  5. The critical path in a project network is the:
  6. PERT stands for:
  7. The study that determines whether a proposed project is technically, economically and financially viable is called a:
  8. Porter's Five Forces model is used to analyze:
  9. In the BCG matrix, a business with high market share in a low-growth market is called a:
  10. A group creativity technique in which ideas are generated freely without criticism is called:

All Engineering Management Reviewer questions