Engineering Board Exam Reviewer · Engineering Management · easy

A dummy activity in an activity-on-arrow network:

  1. Has the longest duration
  2. Shows a logical dependency and consumes no time or resources
  3. Is always on the critical path
  4. Represents an idle worker

Answer

B. Shows a logical dependency and consumes no time or resources

Solution

Dummies keep the network logic correct.

More Engineering Management questions

  1. In PERT, the three time estimates for an activity are:
  2. The critical path in a project network is the:
  3. PERT stands for:
  4. The study that determines whether a proposed project is technically, economically and financially viable is called a:
  5. Porter's Five Forces model is used to analyze:
  6. In the BCG matrix, a business with high market share in a low-growth market is called a:
  7. A group creativity technique in which ideas are generated freely without criticism is called:
  8. A forecasting technique that uses a panel of experts responding anonymously through several rounds is the:
  9. Decisions that are routine, repetitive and handled by established procedures are called:
  10. A statement describing what an organization wants to become in the future is its:

All Engineering Management Reviewer questions