Engineering Board Exam Reviewer · Engineering Management · easy

In PERT, the three time estimates for an activity are:

  1. Early, late and actual
  2. Optimistic, most likely and pessimistic
  3. Start, finish and duration
  4. Normal, crash and float

Answer

B. Optimistic, most likely and pessimistic

Solution

Expected time te = (a + 4m + b)/6.

More Engineering Management questions

  1. The critical path in a project network is the:
  2. PERT stands for:
  3. The study that determines whether a proposed project is technically, economically and financially viable is called a:
  4. Porter's Five Forces model is used to analyze:
  5. In the BCG matrix, a business with high market share in a low-growth market is called a:
  6. A group creativity technique in which ideas are generated freely without criticism is called:
  7. A forecasting technique that uses a panel of experts responding anonymously through several rounds is the:
  8. Decisions that are routine, repetitive and handled by established procedures are called:
  9. A statement describing what an organization wants to become in the future is its:
  10. In a SWOT analysis, which factors are external to the organization?

All Engineering Management Reviewer questions