The critical path in a project network is the:

  1. Shortest path through the network
  2. Path with the most activities
  3. Longest path through the network, which determines the project duration
  4. Path with the lowest cost

Answer

C. Longest path through the network, which determines the project duration

Solution

Any delay in a critical activity delays the whole project.

More Engineering Management questions

  1. PERT stands for:
  2. The study that determines whether a proposed project is technically, economically and financially viable is called a:
  3. Porter's Five Forces model is used to analyze:
  4. In the BCG matrix, a business with high market share in a low-growth market is called a:
  5. A group creativity technique in which ideas are generated freely without criticism is called:
  6. A forecasting technique that uses a panel of experts responding anonymously through several rounds is the:
  7. Decisions that are routine, repetitive and handled by established procedures are called:
  8. A statement describing what an organization wants to become in the future is its:
  9. In a SWOT analysis, which factors are external to the organization?
  10. SWOT analysis evaluates an organization's:

All Engineering Management Reviewer questions