Shortening an activity's duration by adding resources at extra cost is called:

  1. Fast tracking
  2. Leveling
  3. Smoothing
  4. Crashing

Answer

D. Crashing

Solution

Fast tracking overlaps activities that would normally be done in sequence.

More Engineering Management questions

  1. The hierarchical decomposition of a project into smaller, manageable deliverables is called the:
  2. A dummy activity in an activity-on-arrow network:
  3. In PERT, the three time estimates for an activity are:
  4. The critical path in a project network is the:
  5. PERT stands for:
  6. The study that determines whether a proposed project is technically, economically and financially viable is called a:
  7. Porter's Five Forces model is used to analyze:
  8. In the BCG matrix, a business with high market share in a low-growth market is called a:
  9. A group creativity technique in which ideas are generated freely without criticism is called:
  10. A forecasting technique that uses a panel of experts responding anonymously through several rounds is the:

All Engineering Management Reviewer questions