Engineering Board Exam Reviewer · Engineering Management · easy
Shortening an activity's duration by adding resources at extra cost is called:
- Fast tracking
- Leveling
- Smoothing
- Crashing
Answer
D. Crashing
Solution
Fast tracking overlaps activities that would normally be done in sequence.
More Engineering Management questions
- The hierarchical decomposition of a project into smaller, manageable deliverables is called the:
- A dummy activity in an activity-on-arrow network:
- In PERT, the three time estimates for an activity are:
- The critical path in a project network is the:
- PERT stands for:
- The study that determines whether a proposed project is technically, economically and financially viable is called a:
- Porter's Five Forces model is used to analyze:
- In the BCG matrix, a business with high market share in a low-growth market is called a:
- A group creativity technique in which ideas are generated freely without criticism is called:
- A forecasting technique that uses a panel of experts responding anonymously through several rounds is the: