Engineering Board Exam Reviewer · Engineering Management · easy

The hierarchical decomposition of a project into smaller, manageable deliverables is called the:

  1. Work Breakdown Structure (WBS)
  2. Gantt chart
  3. Organizational chart
  4. Critical path

Answer

A. Work Breakdown Structure (WBS)

Solution

The WBS is the basis for scheduling, costing and assigning responsibility.

More Engineering Management questions

  1. A dummy activity in an activity-on-arrow network:
  2. In PERT, the three time estimates for an activity are:
  3. The critical path in a project network is the:
  4. PERT stands for:
  5. The study that determines whether a proposed project is technically, economically and financially viable is called a:
  6. Porter's Five Forces model is used to analyze:
  7. In the BCG matrix, a business with high market share in a low-growth market is called a:
  8. A group creativity technique in which ideas are generated freely without criticism is called:
  9. A forecasting technique that uses a panel of experts responding anonymously through several rounds is the:
  10. Decisions that are routine, repetitive and handled by established procedures are called:

All Engineering Management Reviewer questions