The hierarchical decomposition of a project into smaller, manageable deliverables is called the:
- Work Breakdown Structure (WBS)
- Gantt chart
- Organizational chart
- Critical path
Answer
A. Work Breakdown Structure (WBS)
Solution
The WBS is the basis for scheduling, costing and assigning responsibility.
More Engineering Management questions
- A dummy activity in an activity-on-arrow network:
- In PERT, the three time estimates for an activity are:
- The critical path in a project network is the:
- PERT stands for:
- The study that determines whether a proposed project is technically, economically and financially viable is called a:
- Porter's Five Forces model is used to analyze:
- In the BCG matrix, a business with high market share in a low-growth market is called a:
- A group creativity technique in which ideas are generated freely without criticism is called:
- A forecasting technique that uses a panel of experts responding anonymously through several rounds is the:
- Decisions that are routine, repetitive and handled by established procedures are called: