How many possible two-way communication channels exist in a project team of 10 people?
- 10
- 90
- 45
- 100
Answer
C. 45
Solution
Channels = n(n - 1)/2 = 10(9)/2 = 45.
More Engineering Management questions
- A company has three management levels. The president supervises 8 managers, and each manager supervises 8 supervisors. How many…
- A project requiring an investment of ₱2,000,000 earns a net annual profit of ₱300,000. What is its simple rate of return on investment?
- Equipment costs ₱600,000, has a salvage value of ₱60,000 and a useful life of 9 years. What is the annual straight-line depreciation?
- A product sells for ₱250 and has a variable cost of ₱150 per unit. What is its contribution margin ratio?
- A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule variance (SV)?
- A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the cost variance (CV)?
- A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule performance index (SPI)?
- At a status date, a project has a planned value (PV) of ₱400,000, an earned value (EV) of ₱360,000 and an actual cost (AC) of ₱450,000…
- A project has four activities done one after another, taking 3, 5, 2 and 4 weeks. What is the project duration?
- Operations research techniques such as linear programming are used primarily for: