Engineering Board Exam Reviewer · Engineering Management · medium

A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the cost variance (CV)?

  1. ₱90,000
  2. −₱40,000
  3. −₱90,000
  4. −₱50,000

Answer

C. −₱90,000

Solution

CV = EV - AC = 360,000 - 450,000 = −₱90,000 (over budget).

More Engineering Management questions

  1. A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule performance index (SPI)?
  2. At a status date, a project has a planned value (PV) of ₱400,000, an earned value (EV) of ₱360,000 and an actual cost (AC) of ₱450,000…
  3. A project has four activities done one after another, taking 3, 5, 2 and 4 weeks. What is the project duration?
  4. Operations research techniques such as linear programming are used primarily for:
  5. When an engineer is promoted to manager, the skill that typically becomes MORE important is:
  6. The primary purpose of a cash flow diagram in engineering management is to:
  7. The theory that people are motivated by the belief that effort leads to reward is most closely associated with:
  8. A point outside the control limits on a control chart indicates:
  9. A process is considered capable of meeting specifications (traditional rule) when Cp is at least:
  10. Which of the following is NOT one of the 7 basic quality tools?

All Engineering Management Reviewer questions