Engineering Board Exam Reviewer · Engineering Management · medium

A project has four activities done one after another, taking 3, 5, 2 and 4 weeks. What is the project duration?

  1. 14 weeks
  2. 5 weeks
  3. 3.5 weeks
  4. 120 weeks

Answer

A. 14 weeks

Solution

Sequential activities add: 3 + 5 + 2 + 4 = 14 weeks.

More Engineering Management questions

  1. Operations research techniques such as linear programming are used primarily for:
  2. When an engineer is promoted to manager, the skill that typically becomes MORE important is:
  3. The primary purpose of a cash flow diagram in engineering management is to:
  4. The theory that people are motivated by the belief that effort leads to reward is most closely associated with:
  5. A point outside the control limits on a control chart indicates:
  6. A process is considered capable of meeting specifications (traditional rule) when Cp is at least:
  7. Which of the following is NOT one of the 7 basic quality tools?
  8. The project management document that formally authorizes a project and names the project manager is the:
  9. Resource leveling in project management aims to:
  10. In project management, 'free float' is the amount of time an activity can be delayed without delaying:

All Engineering Management Reviewer questions