A project has four activities done one after another, taking 3, 5, 2 and 4 weeks. What is the project duration?
- 14 weeks
- 5 weeks
- 3.5 weeks
- 120 weeks
Answer
A. 14 weeks
Solution
Sequential activities add: 3 + 5 + 2 + 4 = 14 weeks.
More Engineering Management questions
- Operations research techniques such as linear programming are used primarily for:
- When an engineer is promoted to manager, the skill that typically becomes MORE important is:
- The primary purpose of a cash flow diagram in engineering management is to:
- The theory that people are motivated by the belief that effort leads to reward is most closely associated with:
- A point outside the control limits on a control chart indicates:
- A process is considered capable of meeting specifications (traditional rule) when Cp is at least:
- Which of the following is NOT one of the 7 basic quality tools?
- The project management document that formally authorizes a project and names the project manager is the:
- Resource leveling in project management aims to:
- In project management, 'free float' is the amount of time an activity can be delayed without delaying: