Engineering Board Exam Reviewer · Engineering Management · medium

In project management, 'free float' is the amount of time an activity can be delayed without delaying:

  1. The early start of any immediately following activity
  2. The project completion date
  3. Any critical activity
  4. The project's start

Answer

A. The early start of any immediately following activity

Solution

Total float is the delay possible without delaying the project end.

More Engineering Management questions

  1. A Gantt chart is most useful for:
  2. Enterprise Resource Planning (ERP) systems are designed to:
  3. Material Requirements Planning (MRP) is used to:
  4. The cost of quality category that includes training and quality planning is:
  5. The cost of quality category that includes scrap, rework and warranty claims is:
  6. Total Quality Management (TQM) emphasizes:
  7. Benchmarking is the process of:
  8. Zero-based budgeting requires that:
  9. A budget is best described as a:
  10. The type of plan that is used repeatedly for recurring situations, such as policies and procedures, is called a:

All Engineering Management Reviewer questions