In project management, 'free float' is the amount of time an activity can be delayed without delaying:
- The early start of any immediately following activity
- The project completion date
- Any critical activity
- The project's start
Answer
A. The early start of any immediately following activity
Solution
Total float is the delay possible without delaying the project end.
More Engineering Management questions
- A Gantt chart is most useful for:
- Enterprise Resource Planning (ERP) systems are designed to:
- Material Requirements Planning (MRP) is used to:
- The cost of quality category that includes training and quality planning is:
- The cost of quality category that includes scrap, rework and warranty claims is:
- Total Quality Management (TQM) emphasizes:
- Benchmarking is the process of:
- Zero-based budgeting requires that:
- A budget is best described as a:
- The type of plan that is used repeatedly for recurring situations, such as policies and procedures, is called a: