A Gantt chart is most useful for:
- Showing logical dependencies in detail
- Showing the schedule and progress of activities over time
- Calculating probabilities of completion
- Displaying the organizational hierarchy
Answer
B. Showing the schedule and progress of activities over time
Solution
Simple Gantt charts do not clearly show interdependencies, which network diagrams (CPM/PERT) do.
More Engineering Management questions
- Enterprise Resource Planning (ERP) systems are designed to:
- Material Requirements Planning (MRP) is used to:
- The cost of quality category that includes training and quality planning is:
- The cost of quality category that includes scrap, rework and warranty claims is:
- Total Quality Management (TQM) emphasizes:
- Benchmarking is the process of:
- Zero-based budgeting requires that:
- A budget is best described as a:
- The type of plan that is used repeatedly for recurring situations, such as policies and procedures, is called a:
- Under the Philippine Labor Code, the normal hours of work for an employee should not exceed: