Engineering Board Exam Reviewer · Engineering Management · medium

The project management document that formally authorizes a project and names the project manager is the:

  1. Work breakdown structure
  2. Gantt chart
  3. Project charter
  4. Risk register

Answer

C. Project charter

Solution

It is issued by the project sponsor.