A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule variance (SV)?
- ₱40,000
- −₱40,000
- −₱90,000
- ₱50,000
Answer
B. −₱40,000
Solution
SV = EV - PV = 360,000 - 400,000 = −₱40,000 (behind schedule).
More Engineering Management questions
- A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the cost variance (CV)?
- A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule performance index (SPI)?
- At a status date, a project has a planned value (PV) of ₱400,000, an earned value (EV) of ₱360,000 and an actual cost (AC) of ₱450,000…
- A project has four activities done one after another, taking 3, 5, 2 and 4 weeks. What is the project duration?
- Operations research techniques such as linear programming are used primarily for:
- When an engineer is promoted to manager, the skill that typically becomes MORE important is:
- The primary purpose of a cash flow diagram in engineering management is to:
- The theory that people are motivated by the belief that effort leads to reward is most closely associated with:
- A point outside the control limits on a control chart indicates:
- A process is considered capable of meeting specifications (traditional rule) when Cp is at least: