Engineering Board Exam Reviewer · Engineering Management · medium

A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule variance (SV)?

  1. ₱40,000
  2. −₱40,000
  3. −₱90,000
  4. ₱50,000

Answer

B. −₱40,000

Solution

SV = EV - PV = 360,000 - 400,000 = −₱40,000 (behind schedule).

More Engineering Management questions

  1. A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the cost variance (CV)?
  2. A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule performance index (SPI)?
  3. At a status date, a project has a planned value (PV) of ₱400,000, an earned value (EV) of ₱360,000 and an actual cost (AC) of ₱450,000…
  4. A project has four activities done one after another, taking 3, 5, 2 and 4 weeks. What is the project duration?
  5. Operations research techniques such as linear programming are used primarily for:
  6. When an engineer is promoted to manager, the skill that typically becomes MORE important is:
  7. The primary purpose of a cash flow diagram in engineering management is to:
  8. The theory that people are motivated by the belief that effort leads to reward is most closely associated with:
  9. A point outside the control limits on a control chart indicates:
  10. A process is considered capable of meeting specifications (traditional rule) when Cp is at least:

All Engineering Management Reviewer questions