Engineering Board Exam Reviewer · Engineering Management · medium

A company has three management levels. The president supervises 8 managers, and each manager supervises 8 supervisors. How many supervisors are there?

  1. 16
  2. 24
  3. 64
  4. 512

Answer

C. 64

Solution

8 × 8 = 64 supervisors.

More Engineering Management questions

  1. A project requiring an investment of ₱2,000,000 earns a net annual profit of ₱300,000. What is its simple rate of return on investment?
  2. Equipment costs ₱600,000, has a salvage value of ₱60,000 and a useful life of 9 years. What is the annual straight-line depreciation?
  3. A product sells for ₱250 and has a variable cost of ₱150 per unit. What is its contribution margin ratio?
  4. A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule variance (SV)?
  5. A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the cost variance (CV)?
  6. A project has PV = ₱400,000, EV = ₱360,000 and AC = ₱450,000. What is the schedule performance index (SPI)?
  7. At a status date, a project has a planned value (PV) of ₱400,000, an earned value (EV) of ₱360,000 and an actual cost (AC) of ₱450,000…
  8. A project has four activities done one after another, taking 3, 5, 2 and 4 weeks. What is the project duration?
  9. Operations research techniques such as linear programming are used primarily for:
  10. When an engineer is promoted to manager, the skill that typically becomes MORE important is:

All Engineering Management Reviewer questions