Engineering Board Exam Reviewer · Engineering Management · medium
A line produces 96 units in an 8-hour shift. What is its cycle time?
- 5 minutes per unit
- 12 minutes per unit
- 0.2 minutes per unit
- 8 minutes per unit
Answer
A. 5 minutes per unit
Solution
Cycle time = 480 min/96 units = 5 min/unit.
More Engineering Management questions
- Making a part requires ₱50,000 of fixed tooling plus ₱20 per unit; buying it costs ₱30 per unit. At what quantity are the two options…
- A factory's overhead costs are ₱900,000 per year and it uses 30,000 direct labor hours. What is the overhead rate per direct labor hour?
- Workers took 520 actual hours to complete work worth 468 standard hours. What is the labor efficiency?
- A part requires 6 minutes of machine time. Annual demand is 50,000 parts, each machine is available 2000 hours per year and operates at…
- In the basic EOQ model, if annual demand quadruples while all other factors stay the same, the EOQ will:
- Average monthly demand is 1000 units, and July demand is typically 1300 units. What is July's seasonal index?
- How many possible two-way communication channels exist in a project team of 10 people?
- A company has three management levels. The president supervises 8 managers, and each manager supervises 8 supervisors. How many…
- A project requiring an investment of ₱2,000,000 earns a net annual profit of ₱300,000. What is its simple rate of return on investment?
- Equipment costs ₱600,000, has a salvage value of ₱60,000 and a useful life of 9 years. What is the annual straight-line depreciation?