Engineering Board Exam Reviewer · Engineering Management · medium

Making a part requires ₱50,000 of fixed tooling plus ₱20 per unit; buying it costs ₱30 per unit. At what quantity are the two options equal in cost?

  1. 2500 units
  2. 5000 units
  3. 1000 units
  4. 1667 units

Answer

B. 5000 units

Solution

50,000 + 20Q = 30Q Q = 50,000/10 = 5000 units. Above this, making is cheaper.

More Engineering Management questions

  1. A factory's overhead costs are ₱900,000 per year and it uses 30,000 direct labor hours. What is the overhead rate per direct labor hour?
  2. Workers took 520 actual hours to complete work worth 468 standard hours. What is the labor efficiency?
  3. A part requires 6 minutes of machine time. Annual demand is 50,000 parts, each machine is available 2000 hours per year and operates at…
  4. In the basic EOQ model, if annual demand quadruples while all other factors stay the same, the EOQ will:
  5. Average monthly demand is 1000 units, and July demand is typically 1300 units. What is July's seasonal index?
  6. How many possible two-way communication channels exist in a project team of 10 people?
  7. A company has three management levels. The president supervises 8 managers, and each manager supervises 8 supervisors. How many…
  8. A project requiring an investment of ₱2,000,000 earns a net annual profit of ₱300,000. What is its simple rate of return on investment?
  9. Equipment costs ₱600,000, has a salvage value of ₱60,000 and a useful life of 9 years. What is the annual straight-line depreciation?
  10. A product sells for ₱250 and has a variable cost of ₱150 per unit. What is its contribution margin ratio?

All Engineering Management Reviewer questions