Engineering Board Exam Reviewer · ECE · medium
The Approved Budget for the Contract (ABC) in government procurement is:
- The ceiling price; bids above it are rejected
- The minimum bid
- The contractor's profit
- The bid security amount
Answer
A. The ceiling price; bids above it are rejected
Solution
Bids exceeding the ABC are automatically disqualified.
More ECE questions
- A bidder that is found to have submitted false documents in a government procurement may be:
- Splitting a government contract into smaller amounts to avoid public bidding is:
- Direct contracting (single-source procurement) is generally allowed when:
- Alternative methods of procurement (e.g., direct contracting, shopping, negotiated procurement) may be used:
- The constitutional body that investigates and prosecutes graft cases against public officials is the:
- The Code of Conduct and Ethical Standards for Public Officials and Employees is:
- The government agency that audits the use of public funds, including procurement, is the:
- Under RA 9184, consulting services are generally awarded to the bidder with the:
- Under RA 9184, contracts for goods and infrastructure are generally awarded to the bidder with the:
- The committee in a government agency responsible for conducting the procurement process is the: