Engineering Board Exam Reviewer · ECE · hard

A ₱2,000,000 contract has two approved change orders: an addition of 8% and a deduction of 3% of the original contract price. What is the revised contract price?

  1. ₱2,160,000.00
  2. ₱1,940,000.00
  3. ₱2,100,000.00
  4. ₱2,220,000.00

Answer

C. ₱2,100,000.00

Solution

Net change = +8% - 3% = +5% of 2,000,000 = ₱100,000. Revised price = ₱2,100,000.

More ECE questions

  1. A ₱500,000 balance for a completed radio installation remained unpaid for 2 years after judicial demand. Using the 6% per annum legal…
  2. The Philippine Competition Act, which created the Philippine Competition Commission, is:
  3. A 'kickback' in procurement refers to:
  4. When an engineer believes a client's project will not be successful or economical, ethical practice requires the engineer to:
  5. A dispute resolution process in which a neutral third party helps the parties reach a voluntary settlement, without imposing a decision, is:
  6. The Alternative Dispute Resolution Act of the Philippines is:
  7. The principle that no one shall be unjustly enriched or benefited at the expense of another is found in:
  8. Article 19 of the Civil Code (the 'abuse of rights' principle) requires every person, in the exercise of his rights and performance of his…
  9. In a contract of lease of things, one party binds himself to give to another the enjoyment or use of a thing for:
  10. A contract granting a person the privilege to buy a property within a certain period, for a separate consideration, is called a/an:

All ECE questions