Engineering Board Exam Reviewer · ECE · medium

A dispute resolution process in which a neutral third party helps the parties reach a voluntary settlement, without imposing a decision, is:

  1. Arbitration
  2. Litigation
  3. Mediation
  4. Adjudication by a court

Answer

C. Mediation

Solution

In arbitration, the arbitrator renders a binding award.

More ECE questions

  1. The Alternative Dispute Resolution Act of the Philippines is:
  2. The principle that no one shall be unjustly enriched or benefited at the expense of another is found in:
  3. Article 19 of the Civil Code (the 'abuse of rights' principle) requires every person, in the exercise of his rights and performance of his…
  4. In a contract of lease of things, one party binds himself to give to another the enjoyment or use of a thing for:
  5. A contract granting a person the privilege to buy a property within a certain period, for a separate consideration, is called a/an:
  6. The transfer to a third person of all the rights of the creditor against the debtor (e.g., when a third person pays the debt) is called:
  7. In the absence of a stipulated rate, the legal interest rate on loans or forbearance of money in the Philippines (BSP Circular No. 799…
  8. A ₱6,000,000 contract imposes liquidated damages of 0.1% of the contract price per day, and the procuring entity may terminate when total…
  9. Under the RA 9184 IRR, when the total liquidated damages reach ten percent (10%) of the contract amount, the procuring entity may:
  10. A municipality contracts an ECE firm to design a public address and emergency warning system. During design, the mayor asks the firm to…

All ECE questions