Civil Service Exam Reviewer · Data Interpretation · hard
Schedule for Building a Barangay Hall
Study the Gantt chart below. Each bar shows the weeks during which a task is scheduled (inclusive); bars that overlap in the same week are done at the same time. Use it to answer the questions that follow.
If the foundation is delayed by 2 weeks and every task after it is pushed back by the same 2 weeks, in which week will the project end?
- Week 15
- Week 14
- Week 13
- Week 17
Answer
A. Week 15
Solution
Everything from the foundation onward shifts by 2 weeks, so painting ends in week 13 + 2 = 15.
More Data Interpretation questions
- In how many weeks are TWO tasks scheduled at the same time?
- Which tasks are ongoing during week 10?
- How many weeks does the whole project take?
- Which task takes the LONGEST time?
- If complaints about long waiting time are cut in half next year and all others stay the same, what percent of all complaints will be about…
- What is the SMALLEST number of complaint types that together account for at least 80% of all complaints?
- What cumulative percent of complaints do the top TWO types account for?
- What percent of all complaints were about long waiting time?
- What was the MOST common type of complaint?
- By what percent did renewable generation grow from 2021 to 2025?