Civil Service Exam Reviewer · Data Interpretation · easy
Schedule for Building a Barangay Hall
Study the Gantt chart below. Each bar shows the weeks during which a task is scheduled (inclusive); bars that overlap in the same week are done at the same time. Use it to answer the questions that follow.
Which task takes the LONGEST time?
- Foundation
- Roofing
- Electrical works
- Walls and columns
Answer
D. Walls and columns
Solution
Walls and columns run from week 5 to week 9: 5 weeks.
More Data Interpretation questions
- If complaints about long waiting time are cut in half next year and all others stay the same, what percent of all complaints will be about…
- What is the SMALLEST number of complaint types that together account for at least 80% of all complaints?
- What cumulative percent of complaints do the top TWO types account for?
- What percent of all complaints were about long waiting time?
- What was the MOST common type of complaint?
- By what percent did renewable generation grow from 2021 to 2025?
- What share of the 2025 total came from renewables?
- In which year did renewables FIRST generate MORE electricity than natural gas?
- What was the TOTAL electricity generated in 2025?
- Which source's generation INCREASED every year?