Engineering Board Exam Reviewer · ECE · hard

A written contract for installation of a broadcast system was breached on August 15, 2016. Until when may the injured party file an action based on the written contract, assuming no interruption of prescription?

  1. August 15, 2026
  2. August 15, 2020
  3. August 15, 2022
  4. August 15, 2031

Answer

A. August 15, 2026

Solution

Actions upon a written contract prescribe in 10 years from the time the right of action accrues (Art. 1144).

More ECE questions

  1. A contract requires completion of an installation within 90 calendar days from receipt of the Notice to Proceed, which was received on…
  2. Two contractors agree secretly that one will submit a high 'cover' bid so the other wins a government contract. This practice is called:
  3. A municipality procures a radio system through 'shopping' for an amount far above the limit allowed for that method, and the BAC splits…
  4. An owner verbally agreed with an ECE to design a structured cabling system for ₱80,000. The ECE delivered the design, which the owner…
  5. A contractor and owner signed a contract with a liquidated damages clause of ₱100,000 per day of delay for a ₱1,000,000 installation. The…
  6. A licensed engineer who certifies the installation of a fire detection and alarm system that he never inspected, which later fails during…
  7. Professional liability (errors and omissions) insurance protects an engineer against:
  8. An engineer's 'standard of care' in a negligence case is generally measured by:
  9. The law of the Philippines that penalizes plunder (amassing ill-gotten wealth of at least ₱50 million) by public officers is:
  10. 'In pari delicto' means that when both parties are equally at fault in an illegal contract:

All ECE questions