Engineering Board Exam Reviewer · Engineering Management · medium

Fixed costs are ₱500,000, price ₱250/unit and variable cost ₱150/unit. What is the profit when 8000 units are sold?

  1. ₱1,500,000
  2. ₱800,000
  3. ₱750,000
  4. ₱300,000

Answer

D. ₱300,000

Solution

Profit = Q(P - VC) - FC = 8000(100) - 500,000 = ₱300,000.

More Engineering Management questions

  1. Fixed costs are ₱500,000, the selling price is ₱250 per unit and the variable cost is ₱150 per unit. What are the break-even sales in pesos?
  2. A company has fixed costs of ₱500,000 per year. Its product sells for ₱250 per unit with a variable cost of ₱150 per unit. What is the…
  3. A project uses 3 activities: 8 days at 10 workers, 12 days at 5 workers and 6 days at 8 workers. How many worker-days are required in total?
  4. A project's critical path is 20 days. Two critical activities can be crashed: X at ₱2,000/day (max 2 days) and Y at ₱3,500/day (max 3…
  5. An activity has a normal time of 8 days at a cost of ₱10,000 and a crash time of 5 days at a cost of ₱14,000. What is its crash cost per…
  6. A project has an expected duration of 60 days with a standard deviation of 3 days. What deadline gives a 95% probability of completion? (z…
  7. The critical path of a project has three activities with expected times totaling 36 weeks and variances of 4, 9 and 3 weeks². What is the…
  8. A project has an expected completion time of 48 days and a standard deviation of 2 days along the critical path. What is the probability…
  9. For the project A (3), B (4, after A), C (2, after A), D (5, after B and C), E (3, after C), what is the total float of activity E?
  10. For the project A (3), B (4, after A), C (2, after A), D (5, after B and C), E (3, after C), what is the total float of activity C?

All Engineering Management Reviewer questions