Engineering Board Exam Reviewer · Engineering Management · medium
A project uses 3 activities: 8 days at 10 workers, 12 days at 5 workers and 6 days at 8 workers. How many worker-days are required in total?
- 26 worker-days
- 23 worker-days
- 188 worker-days
- 576 worker-days
Answer
C. 188 worker-days
Solution
8(10) + 12(5) + 6(8) = 80 + 60 + 48 = 188 worker-days.
More Engineering Management questions
- A project's critical path is 20 days. Two critical activities can be crashed: X at ₱2,000/day (max 2 days) and Y at ₱3,500/day (max 3…
- An activity has a normal time of 8 days at a cost of ₱10,000 and a crash time of 5 days at a cost of ₱14,000. What is its crash cost per…
- A project has an expected duration of 60 days with a standard deviation of 3 days. What deadline gives a 95% probability of completion? (z…
- The critical path of a project has three activities with expected times totaling 36 weeks and variances of 4, 9 and 3 weeks². What is the…
- A project has an expected completion time of 48 days and a standard deviation of 2 days along the critical path. What is the probability…
- For the project A (3), B (4, after A), C (2, after A), D (5, after B and C), E (3, after C), what is the total float of activity E?
- For the project A (3), B (4, after A), C (2, after A), D (5, after B and C), E (3, after C), what is the total float of activity C?
- For the project A (3), B (4, after A), C (2, after A), D (5, after B and C), E (3, after C), what is the critical path?
- A project has activities A (3 days), B (4 days, after A), C (2 days, after A), D (5 days, after B and C) and E (3 days, after C). What is…
- A PERT activity has a = 8 weeks and b = 20 weeks. What is its standard deviation?