Engineering Board Exam Reviewer · Engineering Management · medium
A firm uses 40 units per day and supplier lead time is 5 days. With no safety stock, what is the reorder point?
- 200 units
- 45 units
- 8 units
- 35 units
Answer
A. 200 units
Solution
ROP = d × L = 40 × 5 = 200 units.
More Engineering Management questions
- Annual demand is 12,000 units, ordering cost is ₱500/order and holding cost is ₱30/unit/year. What is the total annual inventory (ordering…
- Annual demand is 12,000 units and the EOQ is 632 units. About how many orders are placed per year?
- Annual demand is 12,000 units, ordering cost is ₱500 per order and holding cost is ₱30 per unit per year. What is the economic order…
- If fixed costs increase while price and variable cost remain the same, the break-even quantity will:
- If the selling price per unit increases while fixed and variable costs remain the same, the break-even quantity will:
- A firm has fixed costs of ₱120,000 and variable costs of ₱80 per unit. At what selling price will it break even at 4000 units?
- A company's break-even point is 5000 units and it currently sells 8000 units. What is its margin of safety as a percentage of sales?
- A product has a contribution margin ratio of 40% and fixed costs of ₱500,000. What sales revenue is needed to break even?
- Fixed costs are ₱500,000 per year, price is ₱250/unit and variable cost is ₱150/unit. How many units must be sold to earn a profit of…
- Fixed costs are ₱500,000, price ₱250/unit and variable cost ₱150/unit. What is the profit when 8000 units are sold?