A team of 5 workers produces 400 units in an 8-hour shift. What is the labor productivity?

  1. 10 units per labor-hour
  2. 80 units per labor-hour
  3. 50 units per labor-hour
  4. 2 units per labor-hour

Answer

A. 10 units per labor-hour

Solution

Productivity = 400/(5 × 8) = 400/40 = 10 units/labor-hour.

More Engineering Management questions

  1. Demand for periods 1 to 5 was 10, 12, 15, 17 and 21 units. Using a linear trend (least squares), what is the forecast for period 6?
  2. Actual demand for three periods was 100, 120 and 130 units, while forecasts were 110, 115 and 140 units. What is the mean absolute…
  3. Last period's forecast was 200 units and actual demand was 230 units. Using exponential smoothing with = 0.3, what is the forecast for the…
  4. Sales for the last three months were 120, 135 and 150 units (most recent last). Using weights of 0.2, 0.3 and 0.5 (most recent highest)…
  5. Sales for the last three months were 120, 135 and 150 units. What is the 3-month simple moving average forecast for next month?
  6. A plant produces an item at 200 units/day while demand is 50 units/day (annual demand 10,000). Setup cost is ₱400 and holding cost is…
  7. Annual demand is 4800 units, ordering cost is ₱300 per order, unit cost is ₱80 and the annual carrying cost rate is 25% of unit cost. What…
  8. A company orders 600 units at a time and keeps 100 units of safety stock. What is its average inventory?
  9. A firm uses 40 units per day, lead time is 5 days, and it keeps 60 units of safety stock. What is the reorder point?
  10. A firm uses 40 units per day and supplier lead time is 5 days. With no safety stock, what is the reorder point?

All Engineering Management Reviewer questions