Engineering Board Exam Reviewer · Engineering Management · hard

The first unit takes 50 hours on a 90% learning curve. How long will the 10th unit take? (Tn = T1 nb, b = 0.9/ 2)

  1. 17.43 hours
  2. 45.00 hours
  3. 35.23 hours
  4. 70.95 hours

Answer

C. 35.23 hours

Solution

b = 0.9/ 2 = -0.1520. T10 = 50(10)-0.1520 = 35.23 hours.

More Engineering Management questions

  1. The first unit of a product takes 100 hours. On an 80% learning curve, how long will the 8th unit take?
  2. An assembly line has six tasks totaling 60 minutes per unit. The required cycle time is 20 minutes. If the line is balanced with 4…
  3. A plant operates 480 minutes per day and customer demand is 240 units per day. What is the takt time?
  4. A facility has a design capacity of 50 units/day, an effective capacity of 40 units/day and actual output of 36 units/day. What is its…
  5. A facility has a design capacity of 50 units/day, an effective capacity of 40 units/day and actual output of 36 units/day. What is its…
  6. A shop produces 1000 units worth ₱50 each using 40 labor-hours at ₱150/hr, materials costing ₱8000 and overhead of ₱12,000. What is the…
  7. Labor productivity rises from 10 to 11.25 units per labor-hour. What is the percentage increase?
  8. A team of 5 workers produces 400 units in an 8-hour shift. What is the labor productivity?
  9. Demand for periods 1 to 5 was 10, 12, 15, 17 and 21 units. Using a linear trend (least squares), what is the forecast for period 6?
  10. Actual demand for three periods was 100, 120 and 130 units, while forecasts were 110, 115 and 140 units. What is the mean absolute…

All Engineering Management Reviewer questions