Engineering Board Exam Reviewer · Engineering Management · medium

A machine breaks down 3 times a month, each time stopping a 50-worker line for 8 hours. How many labor-hours are lost per month?

  1. 1200 labor-hours
  2. 150 labor-hours
  3. 400 labor-hours
  4. 24 labor-hours

Answer

A. 1200 labor-hours

Solution

Lost = 3 × 8 × 50 = 1200 labor-hours.

More Engineering Management questions

  1. An equipment investment of ₱500,000 yields net annual savings of ₱180,000. What is its simple payback period?
  2. Project A yields ₱500,000 profit with 60% probability or a ₱200,000 loss with 40% probability. Project B yields ₱300,000 (60%) or ₱50,000…
  3. Maximize Z = 2x + 5y subject to x + y ≤ 4, x + 3y ≤ 6, x ≥ 0, y ≥ 0. What is the maximum value of Z?
  4. Maximize Z = 3x + 2y subject to x + y ≤ 4, x + 3y ≤ 6, x ≥ 0, y ≥ 0. What is the maximum value of Z?
  5. According to Little's law, if 20 customers per hour arrive and each spends an average of 0.25 hour in the system, the average number in…
  6. In an M/M/1 queue with arrival rate 8/hr and service rate 10/hr, what is the average number of customers waiting in line?
  7. In a single-server queue (M/M/1) with arrival rate 8/hr and service rate 10/hr, what is the average time a customer spends in the system?
  8. Customers arrive at a service counter at an average rate of 8 per hour and the server can serve 10 per hour. What is the server utilization?
  9. The first unit takes 50 hours on a 90% learning curve. How long will the 10th unit take? (Tn = T1 nb, b = 0.9/ 2)
  10. The first unit of a product takes 100 hours. On an 80% learning curve, how long will the 8th unit take?

All Engineering Management Reviewer questions